Mortuary Project
Mortuary Project
2019
26 Jun
Start
Our customer sent requests.
29 Jun
Preparing Project
Our project team prepared the project.
01 Jul
Offer
We sent the offer to our customer.
02 Aug
Confirmation
Our customer approved the offer.
05 Aug
Production
Production started.
20 Aug
Shipment
Shipment started.
05 Sep
Assembly
Assembly started.
01 Oct
Completed
The project completed.
Project Information
ROOM TYPES : | 1 x Dual Regime Room |
PROJECT PURPOSE : | Mortuary |
PROJECT AREA : | 22,55 m² |
REFRIGERATION SYSTEMS : | Split Refrigeration System |
DOORS : | 1 x Hinged Chiller Room Door |
PANELS : | 102,92 m² |
Customer Requests
- 68 m³ capacity 1 pc. Dual Regime Room (+2 °C/-18 °C)
Project Detaıls
ROOM NAME | AREA | HEIGHT | ROOM TEMPERATURE | CAPACITY |
DUAL REGIME ROOM | 22,6 m² | 2.8 m | +2 °C / -18 °C | 68 m³ |